Code |
Title |
Status |
D1.1 |
Applications co-design input
Deliverable D1.1: Requirements of all applications for co-design
This deliverable includes all data analytics SW requirements, compute, memory & communication performance, footprints, communication patterns, etc.
|
approved by EC |
D1.2 |
Application use cases and traces
Deliverable D1.2: Application use cases and traces
This second deliverable gathers a description of all the benchmarking necessary to track the increase in performance undergone by each application, in an effective way.
|
approved by EC |
D1.3 |
Application Distribution Strategy
Deliverable D1.3: Application Distribution strategy
This third deliverable gives a detailed partition of each application as well as ist mapping into the MSA.
|
approved by EC |
D2.1 |
DEEP-EST Benchmark Suites
Deliverable D2.1: DEEP-EST benchmark suites
This deliverable report describes set of synthetic and application benchmarks to be used for continuous benchmarking activities described for the Task 2.1.
|
approved by EC |
D2.2 |
Initial Application Analysis and Models
Deliverable D2.2: DEEP-EST Initial Application Analysis and Models
Initial results of the application analysis, modelling approach and first set of models created.
|
approved by EC |
D2.3 |
Benchmarking, evaluation and prediction report
Deliverable D2.3: Benchmarking, evaluation and prediction report
This deliverable presents the main objectives and results for WP2: DEEP- EST benchmark suite created, the evaluation of the scheduling policies, the analysis of the main application characteristic influencing performance scalability based on the performance models and the energy models for the different CPUs and GPUs.
|
approved by EC |
D3.3 |
Tests for Prototype Assessment
Deliverable D3.3: DEEP-EST Tests for Prototype Assessment
Tests to be run on the prototype constructed in WP4 to make sure that it fulfils the specifications and criteria specified in D3.2.
|
approved by EC |
D4.9 |
Final DEEP-EST Prototype Report
Deliverable D4.9: Final DEEP-EST Prototype Report
This document describes the activities and outcome of the prototype hardware development in DEEP-EST.
|
approved by EC |
D5.1 |
Collection of software requirements
Deliverable D5.1: Collection of software requirements
List of requirements that the WP5 and WP6 software must fulfil, and preliminary specification of the overall software architecture.
|
approved by EC |
D5.2 |
Software Specification
Deliverable D5.2: Software Specification
High level specifications of the complete system software stack, including description of interfaces and interdependencies between the packages.
|
approved by EC |
D5.3 |
Prototype Software Implementation
Deliverable D5.3: Prototype Software Implementation
|
approved by EC |
D5.4 |
Complete System-SW Implementation
Deliverable D5.4: Complete System-SW Implementation
This deliverable presents the complete system software implementation from WP5 comprising the full range of functionalities required for interconnect management, network bridging, resource management, job scheduling and monitoring.
|
approved by EC |
D5.5 |
Software Support Report
Deliverable D5.5: Software Support Report
This document puts a focus on the latest developments within the WP5 software stack for the full range of functionality required regarding interconnect management, network bridging, resource management, job scheduling, and system monitoring.
|
approved by EC |
D6.1 |
Design and specification of Programming Environment
Deliverable D6.1: Design and specification of Programming Environment
Detailed specification of the overall programming model.
|
approved by EC |
D6.2 |
Prototype Programming Environment Implementation
Deliverable D6.2: Prototype Programming Environment Implementation
Initial programming environment setup ready to be tested, including all involved components and interfaces.
|
approved by EC |
D6.3 |
Complete Programming Environment Implementation
Deliverable D6.3: Complete Programming Environment Implementation
This deliverable presents the programming environment developed to support the Modular Supercom- puting Architecture (MSA) proposed in the DEEP-EST project.
|
approved by EC |
D6.4 |
Programming environment support report
Deliverable D6.4: Programming environment support report
This deliverable presents the programming environment developed to support the Modular Super- computing Architecture (MSA) proposed in the DEEP-EST project.
|
approved by EC |
D7.1 |
Communication Plan
Deliverable D7.1: Communication Plan
Details of the communication and brand strategy including a toolkit with materials like logos and collateral templates and DEEP EST communication channels.
|
approved by EC |
D7.2 |
Repository Training Material
Deliverable D7.2: Repository Training Material
Design, access information and initial contents for the training repository.
|
approved by EC |
D7.4 |
Policy Briefing
Deliverable D7.4: Policy Briefing
Briefing for political deciders and lobbying groups detailing conclusions from project results and impact on HPC development in Europe.
|
approved by EC |
D7.5 |
Case Study Booklet
Deliverable D7.5: Case Study Booklet
This deliverable provides a brief introduction to the DEEP-EST Early Access Programme and presents the case studies collated from all the completed EAP projects.
|
approved by EC |
D7.6 |
Final Outreach Activity
Deliverable D7.6: Final Outreach Activity
This deliverable presents and discusses the final dissemination activities in the DEEP- EST project.
|
approved by EC |
D8.1 |
Quality Control Plan
Deliverable D8.1: Quality Control Plan
Definition of the quality control processes and templates for internal verification and document review for all project results and deliverables.
|
approved by EC |
D8.8 |
Final report
Deliverable D8.8: Final Report
This report summarizes the objectives, work performed, results achieved and impact of the DEEP-EST project.
|
approved by EC |
Code |
Title |
Status |
D1.1 |
Procedure for Quality Control
Deliverable D1.1: Procedure for Quality Control
This document describes the quality assurance process for the production and approval of deliverables that have to be submitted to the European Commission according to the DEEP- ER Description of Work (Annex I to the Grant Agreement). It also covers presentations and dissemination material based on the provisions laid out in the Consortium Agreement and the Grant Agreement.
|
approved by EC |
D1.2 |
Midterm Management Report at Month 6
Deliverable D1.2: Midterm Management Report at Month 6
This report describes the objectives, work performed, resources used, and achievements during the first six months of the project.
|
approved by EC |
D1.3 |
Midterm Management Report at Month 12
Deliverable D1.3: Midterm Management Report at Month 12
This report describes the objectives, work performed, resources used, and achievements during the first six months of the project.
|
approved by EC |
D1.4 |
Midterm Management Report at Month 18
Deliverable D1.4: Midterm Management Report at Month 18
This report describes the objectives, work performed, resources used, and results achieved during months 12 to 18 of the DEEP-ER project.
|
approved by EC |
D1.5 |
Periodic Progress Report at Month 24
Deliverable D1.5: Periodic Progress Report at Month 24
This report describes the objectives, work performed, resources used, and results achieved during months 13 to 24 of the DEEP-ER project.
|
approved by EC |
D1.6 |
Midterm Management Report at Month 30
Deliverable D1.6: Midterm Management Report at Month 30
This report describes the objectives, work performed, resources used, and achievements during the months 24 to 30.
|
approved by EC |
D1.7 |
Midterm Management Report at Month 36
Deliverable D1.7: Midterm Management Report at Month 36
|
approved by EC |
D1.8 |
Periodic Progress Report
Deliverable D1.8: Periodic Progress Report
|
approved by EC |
D1.9 |
Final report
Deliverable D1.9: Final Report
|
approved by EC |
D2.1 |
Dissemination Plan
Deliverable D2.1: Dissemination Plan
This deliverable describes the planned activities in Work Package 2 “Dissemination, outreach and training” of the EU DEEP-ER project.
|
approved by EC |
D2.2 |
First Report on Dissemination and Training
Deliverable D2.2: First Report on Dissemination and Training
This deliverable reports on the activities and achievements of Work Package 2 “Dissemination, outreach and training“ of the DEEP-ER project during the first project year.
|
approved by EC |
D2.3 |
Second Report on Dissemination and Training
Deliverable D2.3 Second Report on Dissemination
This deliverable reports on the activities and achievements of Work Package 2 “Dissemination, outreach and training“ of the DEEP-ER project during the second project year (October 2014 to September 2015).
|
approved by EC |
D2.4 |
Final Report Dissemination and Training
Deliverable D2.4 Final Report Dissemination
This deliverable reports on the activities and achievements of Work Package 2 “Dissemination, outreach and training“of the DEEP-ER.
|
approved by EC |
D3.3 |
Non-Volatile Memory (NVM) Assessment
Deliverable D3.3: Non-Volatile Memory (NVM) Assessment
This document presents an assessment of the functional and performance characteristics of non-volatile memory (NVM) storage in DEEP-ER.
|
approved by EC |
D3.4 |
Network Attached Memory (NAM)
Deliverable D3.4: Network Attached Memory
This document presents the current status of the Network Attached Memory (NAM). The NAM is a dedicated component that is directly connected to the EXTOLL network within the DEEP-ER system. It can either serve as a (shared) storage or application-specific compute node. For both, the NAM promises to lower the communication overhead on the network.
|
approved by EC |
D3.5 |
Prototype Installation
Deliverable D3.5: Prototype Installation
This document is an updated verson of deliverable 3.5 to reflect the status of the DEEP-ER prototype installation at the end of the project.
|
approved by EC |
D3.6 |
Architecture Review
Deliverable D3.6: Architecture Review
This Deliverable reviews the fundamental architecture decisions as documented in D3.1 and D3.2, plus the relevant high-level aspects of the Eurotech design as described in D8.1.
|
approved by EC |
D4.1 |
Definition of Requirements for I/O
Deliverable D4.1: Definition of Requirements for I/O
This deliverable summarises the application I/O requirements within the DEEP-ER project and introduces the three I/O components, namely, BeeGFS (formerly FhGFS), SIONlib and Exascale10. They address different aspects of I/O within the DEEP-ER project. The application I/O requirements have been systematically addressed through a detailed questionnaire that was submitted to the application developers. This deliverable also explores the inputs needed for these I/O components from the various work packages.
|
approved by EC |
D4.2 |
I/O Interfaces Description
Deliverable D4.2: I/O Interfaces Description
This deliverable describes the different I/O interfaces within the DEEP-ER project, which include the BeeGFS file system, its extensions, and the SIONlib and Exascale10 I/O middleware layers. It briefly describes design concepts and gives an overview of the relevant parts of the API that can be used by DEEP-ER applications to perform I/O efficiently and reliably. This will be of primary interest to applications (WP6) which can exploit these APIs for doing very efficient I/O at scale.
|
approved by EC |
D4.3 |
Definition of test cases and patterns
Deliverable D4.3: Definition of test cases and patterns
This deliverable describes a set of synthetic and application-based benchmarks, which will be used to evaluate the DEEP-ER I/O Architecture with respect to I/O performance, scalability and integration effort.
|
approved by EC |
D4.4 |
IO software packages
Deliverable D4.4: IO software packages
This deliverable describes the three I/O pages that are used in the DEEP-ER project.
|
approved by EC |
D4.5 |
Results of IO Performance Measurements
Deliverable D4.5: Results of IO Performance Measurements
In this deliverable we present the benchmark results and their analyses for different I/O components of the DEEP-ER system.
|
approved by EC |
D5.1 |
Checkpointing Architecture Design
Deliverable D5.1: Checkpointing Architecture Design
This deliverable describes the software architecture that will be developed in the context of the DEEP-ER project to achieve a resiliency level that can effectively scale out on Exascale systems. These systems will require not only stronger resiliency techniques than the current ones but also more flexible and malleable approaches to deal with the heterogeneous nature of DEEP and DEEP-ER proposals.
|
approved by EC |
D5.2 |
Interface Abstraction Layer
Deliverable D5.2: Interface Abstraction Layer
The design of the DEEP-ER system architecture intends to address the need of high resiliency at Exascale. It foresees a multi-staged storage facility to save data needed for a certain job to restart from. The deliverable deals with the appropriate software, which manages the data flows between the application and storage layers, as well as the data transfer between the layers.
|
approved by EC |
D5.4 |
Resiliency Measurements
Deliverable D5.4: Resiliency Measurements
This deliverable presents and analyses the results of the resiliency benchmark measurements conducted for evaluating the resiliency layers developed in the previous tasks of WP5.
|
approved by EC |
D6.3 |
Final Report on Aplication Experience
Deliverable D6.3: Final Report on Aplication Experience
This document reflects the work done and the lessons learned in Work Package 6 (WP6) during the DEEP-ER Project.
|
approved by EC |
D7.1 |
performance extrapolation based on design decisions
Deliverable D7.1: Report on performance extrapolation based on design decisions
This Deliverable investigates the design decisions in light of their effect on system scalability, performance, and energy efficiency, extrapolating application results on the DEEP system.
|
approved by EC |
D7.2 |
Report on projections and improvements for the DEEP, DEEP-ER concept
Deliverable D7.2: Report on projections and improvements for the DEEP, DEEP-ER concept
This document discusses how to scale the DEEP-ER prototype up to Exascale levels and identifies the challenges involved in doing so.
|
approved by EC |
D8.4 |
Manual Aurora Blade Prototype
Deliverable D8.4: Manual Aurora Blade Prototype
This deliverable is a repackaged Operations Manual for the Aurora DEEP-ER Booster Prototype.
|
approved by EC |